Tonnage rates of discharge:
200/300 tonnes per hour

Tonnage load rate:
150/300 tonnes per hour

Quayside storage facilities:
3100 sq m of warehousing

Berwick-upon-Tweed Harbour Commission are the Competent Harbour Authoirty who operate the port, which handles all shipping up to the limitations within the safe tidal Tweed Dock.
 

Dock Maximums

Length 116m
Beam 16.5m
Draft 4.6 (Spring tides)
3.8 (Neap tides)

 There is also an additional jetty adjacent to the Tweed Dock, with a facility to load stone cargoes.